Lodi City Council approves changing water meter budget

Print
Font Size:
Default font size
Larger font size

Posted: Thursday, August 29, 2013 12:00 am

A $700,000 increase to the cost of the water meter project was approved by the Lodi City Council last week, but city staff say the project is still coming in within the original budget.

Knife River Construction of Stockton took on Phase Three of this project in March for about $3 million. Public Works director Wally Sandelin submitted a list of change orders amounting to $771,215.

These included additional repairs and supplies, including asphalt, infill dirt and replacing more pipes than anticipated.

City councilman Bob Johnson submitted a letter to Sandelin asking questions about each change order, wondering why they were needed and why the council didn’t know earlier.

Johnson did not return requests for comment.

The decision was postponed to give council time to go through Sandelin’s response. Last Wednesday, the council approved the decision unanimously.

The seven change orders amounted to a 27-percent increase in project costs. That’s still under the total amount allotted for the project.

Sandelin said change orders are normally under 10 percent of the project total when they are due to rain or unforeseen conditions. Change orders in this phase of the project are additional tasks that came up as the work progressed.

Part of the problem is that Public Works staff are dealing with faulty city records, according to Sandelin. The locations and even existence of 65-year-old asbestos pipes are not always on record, but when workers dig it up, it has to be replaced.

Other changes include moving portions of the project from one phase to another.

Sandelin said he notified the council simply because the numbers were growing rapidly, not because the project was at risk of going over budget.

Sandelin also did not return requests for comment.

Contact reporter Sara Jane Pohlman at sarap@lodinews.com.

More about

More about

More about

Rules of Conduct

  • 1 Use your real name. You must register with your full first and last name before you can comment. (And don't pretend you're someone else.)
  • 2 Keep it clean. Please avoid obscene, vulgar, lewd, racist or sexually oriented language.
  • 3 Don't threaten. Threats of harming another person will not be tolerated.
  • 4 Be truthful. Don't lie about anyone or anything. Don't post unsubstantiated allegations, rumors or gossip that could harm the reputation of a person, company or organization.
  • 5 Be nice. No racism, sexism or any sort of -ism that is degrading to another person.
  • 6 Stay on topic. Make sure your comments are about the story. Don't insult each other.
  • 7 Tell us if the discussion is getting out of hand. Use the 'Report' link on each comment to let us know of abusive posts.
  • 8 Share what you know, and ask about what you don't.

Welcome to the discussion.

Video

Popular Stories

Poll

Should graduations return to the Grape Bowl?

Lodi Unified leaders are moving Lodi and Tokay high school graduations from the Grape Bowl to the Spanos Center at UOP in Stockton. They cite limited seating, costs and unpredictable weather at the Grape Bowl. But others say graduations at the Grape Bowl are an important Lodi tradition, and one reason many supported renovating the stadium. What do you think?

Total Votes: 85

Loading…

Mailing List

Subscribe to a mailing list to have daily news sent directly to your inbox.

  • Breaking News

    Would you like to receive breaking news alerts? Sign up now!

  • News Updates

    Would you like to receive our daily news headlines? Sign up now!

  • Sports Updates

    Would you like to receive our daily sports headlines? Sign up now!

Manage Your Lists